Kota. Change the face of 31 villages in the district and the spindle of hundreds of people thirsting for irrigation and drinking water project has been victim to the slowness of government machinery. Due to the slowness of the project costs have increased nearly twenty millions.
"Right to information" under the state government has informed the spindle irrigation project administrative approval was granted in February 2006. The cost was estimated at Rs 51.81 crore.
So in the last four years the project has taken place only twenty per cent, while the task was to meet up in October 2012. Due to delays in construction of this project cost is estimated at 70 million.
This is the project
Ramganjmandi the spindle to be on the river filling the dam's total capacity is 33.74 million cubic meters, which Ramganjmandi to 3.30 million cubic meters of water use, water will be used to Suket six villages. The remaining seven thousand 386 hectares will be irrigated with water, which will benefit 31 villages.
Dispute over compensation
Yet instead of the displacement of four villages were not marked. Dam to sail close to 166 farmers, 150 hectares of land were Avapt. The land in 2007 rupees per 18 acres of dry land and irrigated area of 45 thousand rupees per bigha was scheduled to be compensated. After protests by farmers of dry land and irrigated area of 50 thousand rupees per bigha compensation of 70 thousand rupees per bigha has been fixed. Farmers are calling it inadequate. He said the area two and a half lakh per bigha rates are on the market.
Committee will decide
Farmers' land surveyors have to replace them. The object of compensation is about 50 farmers, they are protesting. The compensation committee will decide. The work of the project is delayed.
Ishwarlal Kumawat Assistant Engineer (spindle Project), Irrigation Department